Damauli, Jan 20: Under the ongoing Muglin-Pokhara road expansion project, 19.5 km road has been blacktopped. The blacktopping is done from Anbukhaireni to Bandipur of Tanahu district.
Engineer mobilized under the project, Bishnu Prasad Pande, informed that among the blacktopping, there is a two-way pitch in 7.2 km distance.
The blacktopping is now undergoing at Baradi section. It would be carried out on both sides, he added.
The locals and travelers had complained that dusty road had caused sheer inconvenience.
Similarly, a motorable bridge in arc design is being constructed over the Madi River. The bridge, connecting Byas municipality ward no 4 and 5 is constructed at the cost of Rs 210 million.
The Muglin-Pokhara road expansion project is going on with contracts in two phases. RSS