Kathmandu, Aug 30: MCA-Nepal signed a contract for the critical 18 km cross-border electricity transmission line, a critical component of the broader Electricity Transmission Project under the Millennium Challenge Corporation (MCC) Nepal Compact funded by the Government of Nepal and U.S. Government. As MCA-Nepal marks the one-year anniversary of the Compact’s
Progress of the project was shared at a news conference organized here on Wednesday on the occasion of completion of
MCA-Nepal has announced that it signed the final substation contract with Techno Electric and Engineering Company Ltd. (TEECL), India to
The 400 kV Gas Insulated Switchgear (GIS) substation will be constructed within the contract duration of 39 months.
MCA-Nepal has signed a contract with Linxon India Pvt. Ltd. for the construction of the 400 kV New Butwal Substation
Seven different companies have applied for the construction of three electricity substations with the assistance from Millennium Challenge Corporation grant
The cancellation of a contract process for 400 KV transmission line to be constructed under the MCC grant has created
Chief Executive Officer of Millennium Challenge Corporation (MCC), Alice Albright said she was confident and optimistic for timely completion of
CPN (UML) Chairperson KP Sharma Oli and Global Chief Executive Officer of Millennium Challenge Corporation (MCC), Alice Albright, held a
The Chief Executive Officer (CEO) of the American project Millennium Challenge Corporation (MCC) Alice Albright has arrived in Kathmandu.