Dailekh, July 14: Expensive equipment installed for the natural gas and petroleum exploration project at Jaljale in Bhairabi Rural Municipality–1, Dailekh, has begun to rust after remaining unused for an extended period due to delays in launching the project's second phase. Although the first phase of drilling has been completed

According to the Department of Mines and Geology, drilling has been completed up to 3,930 meters depth, with only 70

Almost 79 percent of the drilling work under the exploration of petroleum products has been completed in Jaljale area of

Drilling has been so far carried out up to 218 metres deep in course of petroleum exploration at Bhairabi rural

Five small containers loaded with such equipment arrived here from China via Kolkata and Rupaidiya point. It is said, now

The CPN (UML) Chairman KP Sharma Oli said the exploration of petroleum products in Dailekh district would help achieve the

A dispute surfaced in the process of land purchase for petroleum products exploration has come to an end.