Tanahun, Nov 14: The Chhirkane-Deurali road stretch, part of the under-construction Muglin-Pokhara section, will be closed for four and a half hours daily.
The construction work is being conducted by closing the road section from Byas Municipality-12, Chhirkane to Deurali in two phases.
Project engineer Bishnu Prasad Pandey informed that the road section under the Muglin Pokhara Road Project (Eastern Section) will be completely halted in two phases from November 18 to December 8 to expedite the construction work.
Special arrangements will be made to allow passage for emergency vehicles. “To accelerate road construction in the eastern section of the Muglin Pokhara Road Project, non-essential vehicle movement will be completely closed during this period.”
Currently, 68 percent progress has been made in the eastern section of the Muglin-Pokhara road.
Pandey sait that 14 small bridges, two large bridges, and 103 culverts have been installed along the eastern section.
Construction in the eastern section began on April 15, 2021, after the contract signed on January 1, 2020. The China Communications Construction was awarded the contract for the construction in the eastern section. #highway #nepal #pokhara