Nawalparasi, May 1: A 33-kilometre stretch of the Narayangadh-Butwal section along the East West Highway has been blacktopped. Initially slated for completion within the deadline of 42 months, the project reports a 50 percent accomplishment in over five years and three months. According to Engineer Shiva Khanal, the Information Officer
The expansion of the Narayangadh-Butwal road section under the East-West Highway has been completed by only 46 percent in five
Only 45 percent of the works has been so far completed in Nawalparasi eastern section under the Narayangadh-Butwal road expansion